The 30-inch rule: when your LA deck needs a permit

One measurement decides whether a deck in the City of LA needs a building permit. Here is the rule, what plan check involves, and what an unpermitted deck can cost you later.

Ask around and you will hear everything from "decks never need permits" to "you need one for a single step". In the City of Los Angeles the answer comes down to one measurement, and then to which city your house is actually in.

The 30-inch rule in the City of Los Angeles

The Los Angeles Municipal Code exempts platforms and decks that are no more than 30 inches above grade and are not over a basement or a story below (LAMC §91.106.2, City Clerk copy). A low deck on a flat backyard usually falls under that line. A deck off a second-floor bedroom, a deck over a garage, or a deck built out over a slope does not.

Two things trip people up.

Slopes. A deck can start flush with the back door and be five feet off the ground at the far edge. Measure where the ground drops away, not where you step out. If you are close to 30 inches anywhere, ask before you build.

Exempt is not the same as anything goes. A deck that needs no building permit still has to meet zoning: setbacks from the property line, height limits and, on some lots, hillside rules. It should also be built to the same standard as a permitted deck, because the person standing on it doesn't care whether a permit was required.

What plan check looks like for a deck

When a deck needs a permit, someone draws it up and the Los Angeles Department of Building and Safety reviews it before work starts. Many residential decks can go through LADBS counter plan check, where a plan checker reviews the drawings at the counter and the permit is often issued the same day. Larger or more complicated jobs, such as a tall deck on a steep hillside, can be routed to regular plan check, which takes longer.

A typical deck submission includes:

  • a site plan showing the deck, the house and the property lines
  • a framing plan with joist and beam sizes, spans and spacing
  • footing details: size, depth and how the posts connect
  • the ledger connection to the house, including flashing
  • guardrail and stair details
  • engineering calculations where the design calls for them

After the permit is issued, an inspector usually visits at key stages, typically the footing holes before concrete, the framing before the boards cover it, and a final. Each inspection is a second set of eyes on the parts of the deck you will never see again once it is finished.

Your mailing address may not be your building department

"Los Angeles" on the envelope doesn't mean the City of Los Angeles approves your deck. Malibu, Santa Monica, Beverly Hills, West Hollywood, Burbank, Glendale and Calabasas all run their own building departments, with their own forms and rules. Malibu adds coastal permits to the mix. Unincorporated areas go through LA County. In Ventura County, Thousand Oaks and Simi Valley run their own building divisions too. LADBS rules, including the 30-inch exemption, apply only inside City of LA limits. Your property tax bill or the county assessor's map will tell you which jurisdiction you are in.

Why an unpermitted deck comes back to bite

An unpermitted deck tends to surface when the house changes hands. A buyer's home inspector notes the deck and asks whether it was permitted. The buyer's agent checks the permit history. California's seller disclosure form asks whether alterations or repairs were made without the necessary permits, so a seller who knows has to say so.

From there the buyer can ask for a price reduction, ask for the deck to be permitted, or ask for it to come down. Permitting a deck after it is built is possible, but the inspector still needs to see the footings and framing, so it can mean opening up finished work. A deck that would not have passed in the first place may have to be rebuilt. Paying for the permit up front almost always costs less than any of that.

The same is true when you apply for permits on other work. A building department reviewing your kitchen addition can notice the deck out back that has no permit on file.

Hire someone licensed, and check

In California, anyone who takes on a construction job worth $1,000 or more, counting labour and materials, needs a contractor's licence. Since AB 2622 took effect in January 2025, that $1,000 threshold applies only when the job does not need a building permit (CSLB bulletin on AB 2622). Any deck that needs a permit needs a licensed contractor, whatever the size of the job, unless you take it on yourself as an owner-builder.

Checking takes a minute. Put the licence number from the bid into the CSLB licence lookup. It shows whether the licence is active, the classification (a B, General Building, covers carpentry such as decks), and whether workers' compensation insurance is on file. Ours is CSLB #1122454.

Be wary of anyone who suggests skipping the permit to save time, or who asks you to pull it in your own name. The permit protects you, not the contractor.

How we handle it

Whenever a job needs a permit, we pull it, and the drawings and inspections are part of the job rather than an extra you chase. Permits and our process explains what happens from the estimate to the final sign-off.

Free on-site estimate

Let's look at your yard.

Tell us a little about the project and we'll set up a free on-site estimate. We reply within one business day.

Rather talk now? (818) 245-5541

Photos optional
Up to 6. A wide shot and a close-up of anything worn or broken let us take a look before the visit.

We use your details only to reply about your project. See our privacy policy.

Before you go

Still picturing the deck? Let's look at it together.

Leave a name and number and we'll call to set up a free on-site estimate. We'll look at the yard, the slope and the sun with you. No obligation.

Rather call now? (818) 245-5541 What a deck costs in LA

We reply within one business day. See our privacy policy.